    摘要:

    利用考虑时间因子的有限元方法研究了钢框架-钢筋混凝土核心筒混合体系的竖向变形差问题.分析表明,施工方案中的时间参数可以确定结构计算中需要考虑的混凝土收缩徐变的数量和参与作用的时间,从而使混凝土收缩徐变对体系竖向变形差以及各构件内力分配的影响发生明显变化.适当增大结构混凝土部分相对于钢结构部分提前施工的层数是减小混凝土收缩徐变效应的较好方法.

    Abstract:

    By using the finite element method with consideration of time factor, the vertical differential shortening and member internal forces of steel frame-reinforced concrete corewall structures were analyzed. The studies show that the amount and the involvement time of concrete shrinkage and creep are determined by the time parameters in construction scheme, which change the effect of concrete shrinkage and creep obviously. To reduce the effect of shrinkage and creep, it is a good method to appropriately increase the number of floors of concrete corewall before the steel frame is constructed.

    参考文献
    相似文献
    引证文献
文章指标
  • PDF下载次数:
  • HTML阅读次数:
  • 摘要点击次数:
  • 引用次数:
引用本文

黄湘湘,周绪红.施工时间参数对混合体系竖向变形差的影响[J].湖南大学学报:自然科学版,2015,42(3):89~93

复制
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2015-04-09
  • 出版日期:
作者稿件一经被我刊录用,如无特别声明,即视作同意授予我刊论文整体的全部复制传播的权利,包括但不限于复制权、发行权、信息网络传播权、广播权、表演权、翻译权、汇编权、改编权等著作使用权转让给我刊,我刊有权根据工作需要,允许合作的数据库、新媒体平台及其他数字平台进行数字传播和国际传播等。特此声明。
关闭